Charleston County Council approved allocating Transportation "Half-Cent" Sales Tax funding in the amount of up to $1 million for drainage improvements per fiscal year. Engineering design, traffic studies, and a public involvement process to gather input from residents on proposed improvements will all be the first steps. Some of these projects may be funded for multiple years to provide for engineering design, right-of-way acquisition (if necessary), and construction. Visit this Web site throughout the process to review projected schedules and public meeting dates.
FY 2006 Drainage Improvement Projects
Three watershed / drainage improvement projects began in 2005. Engineering design services are currently underway for the following areas:
The Charleston County RoadWise Utility Coordinator, Raymond Hunter, interacts with the various utility companies affected by the Isaac German Watershed project. The majority of the utility coordination for this project was confirmed during the Rifle Range/Porchers Bluff intersection improvement project.
FY 2007 Drainage Improvement Projects
| Project Name |
Location |
Project Status |
| Scotia, Baker, and Morrison Drainage Improvements |
McClellanville |
Design complete |
| West Hudson Avenue Drainage Improvements |
Folly Beach |
Construction complete |
| Lincolnville Drainage Improvements |
Lincolnville |
Design complete |
| St. Paul's Drainage Study |
Ravenel/Hollywood/Meggett area |
Study complete |
FY 2008 Drainage Improvement Projects
| Project Name |
Location |
Project Status |
| Legareville Drainage Study |
Johns Island |
Study is underway |
|