December 2009 - This photograph shows where the curb and gutter has been poured at the South End of Segment 1. A sidewalk has been installed and stone base and asphalt has been placed in the north and southbound lanes of the new roadway.
|
|
December 2009 - This photograph shows the curb and gutter for the median on the south end of Segment 2.
|
|
December 2009 - This photograph shows workers installing deck forms and reinforcing steel on Bridge 1 over the Meandering Stream.
|
|
December 2009 - This photograph shows 65% of the clearing operations are complete in Segment 3. Approximatley 1,200 feet of the southbound lane was fine graded and stone base has been placed.
|
|
November 2009
Moving earth on Segment 3
|
|
November 2009
Bridge deck work on bridge site #1
|
|
November 2009
Grading and surveying at the beginning of Segment 3.
|
|
|
|
|
|
September 18, 2009
Workers grading the slope on the roadside of Segment #3
|
|
September 18, 2009
Workers building the MSE wall by Bridge site #1
|
|
September 18, 2009
Workers completing the pile driving operations on Bridge 1 (Left side).
|
|
July 24, 2009
Workers preparing for bridge pilings.
|
|
July 24, 2009
Workers preparing for new sidewalks at the intersection of Ashley Phosphate Road.
|
|
July 15, 2009
Installation of drainage pipe and catch basin along the new roadway in Segment 2.
|
|
July 15, 2009
Staging materials for the first bridge structure.
|
|
June 16 - Workers preparing the roadbed by mucking and hauling unstable soil.
|
|
June 16 - Clearing for bridge site.
|
|
June 4, 2009 - Concrete pour for culvert in Segment 2.
|
|
June 4, 2009 - Roller packing the sub-grade of the roadway in Segment 2.
|
|
May 20, 2009 - Paving a section of North Spartan Boulevard
|
|
May 20, 2009 - Inspector testing concrete.
|
|
April 19, 2009
Dumping base course prior to paving.
|
|
April 19, 2009
Spreading base course prior to paving.
|
Construction Progress Photos
As construction continues, photos will be taken from the same two spots to show construction progress. One area is the beginning of the project where Palmetto Commerce Parkway Phase 1 ends, and the second area is the end of the project where North Spartan Boulevard intersects with Ashley Phosphate Road.
|
November 2009
Beginning of project at the end of Palmetto Commerce Parkway Phase I.
|
|
November 2009
End of project at Ashley Phosphate Road.
|
|
September 2009
Beginning of project at the end of Palmetto Commerce Parkway Phase I.
|
|
September 2009
End of project at Ashley Phosphate Road.
|
|
July 2009 - The beginning of Palmetto Commerce Parkway Phase II that connects to Palmetto Commerce Parkway Phase I. Large rocks and piles of dirt will be used during construction.
|
|
July 2009 - Newly paved Ashley Phosphate Intersection looking south. This is the end of the project.
|
|
June 2009
Start of construction at the end of Palmetto Commerce Parkway Phase I.
|
|
June 2009
Start of construction at the end of the project on North Spartan Boulevard at Ashley Phosphate Road. Photo shows new curb where North Spartan meets Ashley Phosphate Road.
|
|
May 2009
Start of construction at the end of Palmetto Commerce Parkway Phase I.
|
|
May 2009
Start of construction at the end of the project on North Spartan Boulevard at Ashley Phosphate Road. Photo shows new curb and gutters.
|
|
April 2009
Start of construction at the end of Palmetto Commerce Parkway Phase I. Large piles of dirt will be used during construction.
|
|
April 2009
Start of construction at the end of the project on North Spartan Boulevard at Ashley Phosphate Road. Photo shows new curb and gutters.
|
|
March 2009
Start of construction at the end of Palmetto Commerce Parkway Phase I. Large piles of dirt will be used during construction.
|
|
March 2009
Start of construction at the end of the project on North Spartan Boulevard at Ashley Phosphate Road. Photo shows new curb and gutters.
|
|
February 2009
Start of construction at the end of Palmetto Commerce Parkway Phase I.
|
|
February 2009
Start of construction at the end of the project on North Spartan Boulevard at Ashley Phosphate Road.
|
|
January 2009
Start of construction at the end of Palmetto Commerce Parkway Phase I.
|
|
January 2009
Start of construction at the end of the project on North Spartan Boulevard at Ashley Phosphate Road.
|